The Wave Twin Rinks, is a state of the art facility offering 2 NHL ice rinks, 2 mini rinks, a sports medicine clinic, a dryland training facility and gym and a fully licensed restaurant and bar – overlooking the two main ice pads.
The Wave Twin Rinks
2018
Co-generation Power generation system
ProPhase was hired to install a Co-generation system consisting of 2 x 340 kW MAN gas engines and 1 x 500 kW Cummins diesel engine at Twin Rinks to provide reliable and stable power to the facility, while reducing energy costs and minimizing emissions into the atmosphere. ProPhase and Burlington Hydro worked together to allow parallel connection to commission generators, eliminating the load bank.
Identifying specific baseline and peak power demands from the facility in order to properly size the co-generation system.
Making sure project managers and key stakeholders align on project goals, timelines, and expectations.
For each aspect of the project, ProPhase’s team consisted of experts in their respective fields to ensure high-quality work.
Maintaining a clean safety record and ensuring the wellbeing of all workers and Twin Rinks' employees.
By scheduling during off-hours, ProPhase reduced any impact on Twin Rinks' operations and customer experience.
ProPhase installed robust communication and data infrastructure, ensuring reliable connectivity and data flow across the store locations. This included fiber optic cabling, network setup, and data center installations.
Comprehensive electrical systems were installed, including lighting, power distribution, and emergency power systems. ProPhase’s attention to detail ensured that all installations met Target’s high standards for safety and reliability.
Energy-efficient cogeneration systems were implemented to provide stable and cost-effective power. These systems not only reduced energy costs but also contributed to a lower carbon footprint, aligning with Twin Rink’s sustainability goals.
Advanced building automation systems were installed to optimize energy usage, enhance security, and improve overall operational efficiency. These systems provided real-time monitoring and control over various building functions.
We partnered with Twin Rinks to implement strategic improvements and optimize processes, resulting in a remarkable increase in overall efficiency.
The integration of a co-generation system enhanced overall energy efficiency, reducing energy costs.
The cogeneration system significantly reduces their energy costs, providing a stable power supply and supporting Twin Rinks’ sustainability initiatives.
ProPhase’s meticulous approach to electrical installations ensured a reliable and safe power infrastructure, minimizing the risk of outages and accidents.
Twin Rinks has improved control over their facilities, resulting in better energy management and reduced emissions.
Before concluding the project, ProPhase ensures that all systems are fully operational and meet the client’s expectations:
Performing extensive testing of all systems to ensure they function correctly and efficiently.
Offering training sessions for Twin Rinks' staff to ensure they are well-versed in operating and maintaining the new systems.
Conducting a final review with Twin Rinks' management to confirm satisfaction and officially hand over the project.
ProPhase’s commitment to excellence extends beyond project completion:
Providing post-installation support and maintenance to ensure long-term reliability and performance of the installed systems.
Encouraging feedback from Twin Rinks to continually improve services and address any future needs promptly.
Partner with ProPhase today to see how you can generate immediate savings and an attractive ROI.
Terms of use | Privacy Environmental Policy